You are here : Home / Project
Projects
    abcd

    networking

    ghhjfhjhf

    hjgughy


    Rj Corp Datacentre Migration with Revamp

    asheesh garg

    IT Infrastructure Deployment @ Toll Plazas

    Scope includes Supply, Installation, Testing ,and Commissioning of IT infrastructure at various Toll Plazas.

    eValue Serve.com DataCentre Build

    Design, Supply , Installation, Testing of Tier 3datacenter of Electrical, (including UPS, Panels, Lighting, Earthing, cabling),Precision Cooling Solution, IBMS, racks, Rack PDU, and complete civil works.

    Supply and Installation of CCTV cameras at Ministry of Power, Shram Shakti Bhawan, New Delhi

    Design, Supply, Installation, and Implementation of Surveillance Solution CCTV cameras at Ministry of Power , Shram Shakti Bhawan.

    Supply, Installation , Testing , and Commissioning of Access And Visitor Management Solution at NBCC Bhawan

    Scope of Work includes Supply, Installation, Testing and Commissioning of Customised Access Control and Visitor Management Solution .

    Facility Management Services and Maintenance of Surveillance Systems at Chennai Airport.

    Scope of Work includes on -site manpower support , facility management and maintenance of SCCTV at Chennai Airport.

    Augmentation of HP Unix Blade Servers & Software Augmentation at Airports Authority of India IT Datacentre

    Scope of Work includes the Supply,Installation, Testing and Commissioning of Augmentation of HP Itanium Servers with software upgrade and licenses in the Airports Authority of India IT datacentre.



    Enterprise Management Software Implementation ( Sun Microsystems)

    Implementation and one year support for Enterprise Management Software to Sun Microsystems including Unicentre Network and Systems Management Managed Resource for Windows/ Linux , Microsoft exchange server, and CA Access Control.



    TCIL – eProcurement Portal ( IT hardware )

    Upgrading TCIL present Data Centreinfrastructure at T.C.I.L Bhawan, New Delhi and implementing latest and proven technologies for Hardware, Softwareand related infrastructure and to integrate the same with present IT Infrastructure.

    The scope included Supply,Installation and Commissioning of hardware equipment for Data Centre ; Supply,Installation, Integration and Commissioning of Software ; Integration ofpresent infrastructure with New proposed IT infrastructure ; Training to stafffor operation, maintenance and administration at TCIL premises.


    DFCC – Datacenter, Delhi.

    Scope included Designing, Renovation and Implementation of Precision Air Conditioning , Comfort Air Conditioning with related earthing and electrical .

    ORANGE ( HPPCL) – Datacenter, Shimla

    HPPCL (Himachal Pradesh Power Corporation Limited) commenced a major project towards deployment of ERP systems and their integration with various business functions. To support the ERP platform & host its hardware HPPCL  envisaged building a state of art Data Centre at its own premises.

    The scope included Design and build an in-house Data Centre (including NOC facility) at HPPCL facility in terms of the civil, electrical and mechanical work required to build the Data Centre; Supply,installation and commissioning of the Data Centre facility Infrastructure.

    Technologies Implemented :

    Tier 3 datacentre set up at Shimla included state –of-the-art technologies like Modular UPS systems with hot-swappable and redundant  components of batteries, power modules and control modules ; In-Row Cooling DX based systems and DatacentreMonitoring tool with online PUE monitoring tool.


    CONCOR – Datacenter, Delhi.

    Expansion of Datacenter for installation of High-End servers at CONCOR, ICD Tughlaqabad, Delhi.

    The scope included Supply and Installation of Intelligent fire Alarm System , Intelligent Fire suppression system FM200/NOVEC1230, High Sensitivity smoke detection system , Civil work, Precision Air conditioning system for server, Comfort Air Conditioning System, Rodent Repellant system for Datacentre and Electrical Distribution work in New Datacentre Key Technologies Implemented :

    Deployment of tandem scroll compressor DX based  Precision Air Conditioners for ensuring High Sensible Ratio for server room critical applications. Deployment of safety and security infrastructure.


    BSNL – Precision cooling , PAN India.

    Deployment of Microprocessor based high precision air conditioning package AC for 16 sites across India in (N+1) mode at RMCDC sites.



    NIIT Technologies ( AAI ) – Datacenters at Chennai, Kolkata,

    Scope of Work includes Supply, Installation ,Testing and Commissioning of Establishment of Airport Operations ControlCenters (AOCC).SITCof Operator console with furniture, Desktop Ups for Workstation , UPS for Videowall , Fire detection and control system , Fire suppression system, AccessControl system , Rodent repellent system , Water leak detection system ,Building management system , Power distribution system , Earthing items ,Lighting & fittings , Symmetra PX modular UPS , Racks & Accessories ,Conduits  , Raceway , Cable trays , CivilWorks in AOCC and DC , Precision Air Cooling/AC , VESDA , Data centreMonitoring & Management , Structured Cabling & Passive Network ,Electrical Cabling in AOCC and DC , Project Management .

    Technologies Implemented :

    Tier 3 datacentre set up included state –of-the-art technologies like Modular UPS systems with hot-swappable andredundant  components of batteries, powermodules and control modules ; In-Row cooling DX based systems / in-Row coolingwith air cooled chillers and hot aisle containment ; Datacentre InfrastructureManagement /Monitoring tool with online PUE monitoring tool .


    NIIT Technologies ( AAI ) – Datacenters at Pune, Jaipur, Calicut, Thiruvananthapuram,

    Scope of Work includes Supply, Installation ,Testing and Commissioning of Establishment of Airport Operations ControlCenters (AOCC).SITCof Operator console with furniture, Desktop Ups for Workstation , UPS for Videowall , AccessControl system , Power distribution system , Earthing items ,Lighting & fittings , Symmetra PX modular UPS , Racks & Accessories ,Conduits  , Raceway , Cable trays , CivilWorks in AOCC and DC , Precision Air Cooling/AC , , Structured Cabling & Passive Network ,Electrical Cabling in AOCC and DC , Project Management .

    Technologies Implemented :

    Tier 2 datacentre set up included state –of-the-art technologies like Modular UPS systems with hot-swappable andredundant  components of batteries, powermodules and control modules ; In-Row cooling DX based systems .


    NIIT Technologies ( AAI ) – Datacenters at Mangalore, Guwahati ,Trichi, Ahemedabad

    Scope of Work includes Supply, Installation ,Testing and Commissioning of Establishment of Airport Operations ControlCenters (AOCC). SITC of Operator console with furniture, Desktop Ups for Workstation , UPS for Videowall , Access Control system , Power distribution system , Earthing items ,Lighting & fittings , Symmetra PX modular UPS , Racks & Accessories ,Conduits  , Raceway , Cable trays , CivilWorks in AOCC and DC , Precision Air Cooling/AC , , Structured Cabling & Passive Network ,Electrical Cabling in AOCC and DC , Project Management .

    Technologies Implemented :

    Tier 2 datacentre set up included state –of-the-art technologies like Modular UPS systems with hot-swappable and redundant  components of batteries, power modules and control modules ; In-Row cooling DX based systems .


    Airports Authority of India (Datacenter) – Delhi

    Scope included Designand Site Preparation of the proposed Data Centre in terms of the civil,electrical and mechanical work required to build the Data Centre includingfalse ceiling, false flooring, moisture sealing and fortification of thewindows and all other necessary components ; Supply, installation and settingup of the necessary basic Infrastructure (State of Art UPS and Air-ConditioningSystem, Fire Detection and Control System, , Lighting system, Fire Detectionand Control system, Power Cabling etc.); Supply, installation and setting up ofthe multi-layer Physical Security infrastructure like bio-metric basedaccess-control system, CCTV/ surveillance systems ; Five years on-sitemaintenance of all the equipments and their components supplied in setting upthe basic infrastructure in the proposed Data Centre; Onsite support for DataCentre Infrastructure Operations on 24*7*365 basis by qualified engineers/personnel for a period of five years to ensure more than 99.98% serviceavailability.

    Technologies Implemented :

    Tier 3 datacentre set up included state –of-the-art technologies like Modular UPS systems with hot-swappable andredundant  components of batteries, powermodules and control modules ; In-Row cooling DX based with hot aisle containment,metered PDUs ; Datacentre Infrastructure Management System.


    AVIVA Life Insurance (Datacenter) – Gurgaon

    Scope included Design and Site Preparation of theproposed Data Centre in terms of the civil, electrical and mechanical workrequired to build the Data Centre including Supply, installation and setting up of the necessary basicInfrastructure (State of Art UPS and Air-Conditioning System, Fire Detectionand Control System, Fire Detection and Control system, PowerCabling etc.)

    Technologies Implemented :

    First In-Row cooling installation in India for APC .Tier 3 datacentre set up included state –of-the-art technologies like Modular UPS systems with hot-swappable andredundant  components of batteries, powermodules and control modules ; In-Row cooling DX based metered PDUs ; Datacentre Infrastructure Management System.


    NDPL (Datacenter) – Delhi

    Scope included Designand Site Preparation of the Data Centre in terms of Racks, iPDU, Cabletroughs, State of the Art Modular UPS with Modular power distribution; Onsitesupport for Data Centre Infrastructure Operations on 24*7*365 basis byqualified engineers/ personnel  to ensure more than 99.5% service availability.



    Metlife Insurance (Datacenter) – Gurgaon

    Scope included Design and Site Preparation of theproposed Data Centre in terms of the civil, electrical and mechanical workrequired to build the Data Centre including false ceiling, false flooring,moisture sealing and fortification of the windows and all other necessarycomponents ; Supply, installation and setting up of the necessary basicInfrastructure (State of Art UPS and Air-Conditioning System, Fire Detectionand Control System, , Lighting system, Fire Detection and Control system, PowerCabling etc.); Supply, installation and setting up of the multi-layer PhysicalSecurity infrastructure like bio-metric based access-control system, CCTV/surveillance systems ;

    Technologies Implemented :

    Tier 3 datacentre set up included state –of-the-art high efficiency IGBT based UPS systems with batteries, DX based Precision Air Conditioning  metered PDUs.


    DIMTS (Operations Command Centre) – Delhi

    Scope included Development of Command and Control center ( DCCC)  for Traffic System at ISBT Kashmere Gate, NewDelhi on Design and Build basis for creating creating a state-of-the-artData & Command Centre, which would host Applications servers, networkinfrastructure, monitoring screens, storage, reception etc.

    Catalyst Business Solutions (Datacenter) – Delhi

    Scope included Design and Site Preparation of theproposed Data Centre in terms of the electrical and mechanical workrequired to build the Data Centre including Supply, installation and setting up of the necessary basicInfrastructure (State of Art UPS and Air-Conditioning System, Fire Detectionand Control System, , Lighting system, Fire Detection and Control system, PowerCabling etc.); Supply, installation and setting up of the multi-layer PhysicalSecurity infrastructure like bio-metric based access-control system, CCTV/surveillance systems.

    Technologies Implemented :

    Tier 3 datacentre set up included state –of-the-art technologies like Modular UPS systems with hot-swappable andredundant  components of batteries, powermodules and control modules ; In-Row cooling with air cooled chillers and hot aisle containment based ,metered PDUs ; Datacentre Infrastructure Management System.


    AVIVA Life Insurance (Disaster Recovery Centre) – Chennai

    Scope included Design and Site Preparation of theproposed Data Centre along with facility rooms, NOCs , Electrical, BMS rooms, complete in terms of the civil, electrical and mechanical workrequired to build the Data Centre including false ceiling, false flooring,moisture sealing and fortification of the windows and all other necessarycomponents ; Supply, installation and setting up of the necessary basicInfrastructure (State of Art UPS and Air-Conditioning System, Fire Detectionand Control System, , Lighting system, Fire Detection and Control system, PowerCabling etc.); Supply, installation and setting up of the multi-layer PhysicalSecurity infrastructure like bio-metric based access-control system, CCTV/surveillance systems.

    Technologies Implemented :

    Tier 3 datacentre set up included state –of-the-art technologies like Modular UPS systems with hot-swappable andredundant  components of batteries, powermodules and control modules ; In-Row cooling with air cooled chillers with hot aisle containment,metered PDUs ; Datacentre Infrastructure Management System ; PUE monitoring tools.


    Schneider Electric India Limited (Datacenter PM) – Hyderabad

    Scope included Project Coordination and Management forDatacentre site of Tata Teleservices Limited at Shamshabad, Hyderabad for 3150KVA Transformers , 1500 KVA DG sets , 33 KV HT Panel, LT & distributionpanels, 400 KVA UPS, BBT, IBMS, 600 TR Air cooled screw chillers, 600 TR watercooled centrifugal chillers, PAHU package , etc.

    Airports Authority of India (Datacenter) – Kolkata & Chennai

    Scope included Design and Site Preparation of theproposed Data Centre in terms of the electrical and mechanical workrequired to build the Data Centre including false flooring,moisture sealing and fortification of the windows and all other necessarycomponents ; Supply, installation and setting up of the necessary basicInfrastructure (State of Art UPS and Air-Conditioning System, Fire Detectionand Control System,  Fire Detection and Control system, PowerCabling etc.); Supply, installation and setting up of the multi-layer PhysicalSecurity infrastructure like bio-metric based access-control system, CCTV/surveillance systems.

    Technologies Implemented :

    Tier 3 datacentre set up included state –of-the-art technologies like Modular UPS systems with hot-swappable andredundant  components of batteries, powermodules and control modules ; In-Row cooling DX based with metered PDUs ; Datacentre Infrastructure Management System.


    MCD Civic Center (UPS) – Delhi

    Scope included Supply, Installation, Testing and Commissioning of 1.2

    MVAUPS  with battery bank for MCD CivicCentre, New Delhi – the tallest building in Delhi.


    Max, Batra, Apollo, Sir Gangaram, Rajiv Gandhi Cancer Hospitals (UPS) – Delhi

    Scope includedSupply, Installation , Testing and Commissioning of large capacity UPS for critical equipments and areas within the hospitals.

     



    Honeywell Automation India Ltd. (Kolkata Airport PAVA) - Kolkata

    Scope included Supply, Installation,Testing and Commissioning of Public Announcement and Voice Alarm System at Kolkata International Airport.